Earned Value Management (EVM) Dashboard
Enter 4 numbers from your project and instantly see if you're on track for budget and schedule — with colour-coded results and a cost forecast at completion.
Project Values
Enter amounts in any currency — the dashboard works with the ratios.
Total approved budget for the project.
📄 Where to find it: project charter, approved budget baseline, or signed contract value.
Budgeted cost of work scheduled to be done by today.
📄 Where to find it: schedule baseline. Multiply % planned to date by BAC. If 50% was planned, PV = 50% × BAC.
Budgeted cost of work actually completed to date.
📄 Where to find it: progress reports. Multiply % actually done by BAC. If 45% is done, EV = 45% × BAC.
Real cost incurred for work completed to date.
📄 Where to find it: accounting system, timesheets, invoices, or cost reports — all costs spent so far.
Please fill in all four fields before calculating.
Forecast Final Cost
Cost Efficiency
CPI = EV ÷ AC
SPI
Schedule
CV
Cost Variance
EV − AC
SV
Schedule Var.
EV − PV
Supporting Forecasts
ETC — Remaining Cost
How much more budget you'll need to finish.
VAC — Budget Impact
Projected savings or overrun at completion.
Scenario Analysis
Alternative EAC formulas · TCPI
Scenario Analysis
Alternative EAC formulas · TCPI
Not sure which EAC to use? Start with EAC (BAC ÷ CPI) shown above — it's the most common and assumes your current efficiency continues to the end.
EAC (planned rate)
AC + (BAC − EV) — if remaining work proceeds at the original planned rate
EAC (CPI × SPI)
AC + [(BAC − EV) ÷ (CPI × SPI)] — weighted for both cost and schedule inefficiency
TCPI (BAC)
Efficiency needed to stay within original budget.
TCPI (EAC)
Efficiency needed to hit the revised forecast.
Performance Trend
Timeline estimated from schedule completion (PV ÷ BAC). Dashed lines show plan and EAC projection.
Coming Soon
PMP Study Hub — Built for Busy Professionals
A structured study system for the new PMP ECO 2026 exam. Planner, flashcards, drills, and mock exams — all built around 30–90 minutes a day.
EVM Formula Reference
A quick reference for every key EVM metric.
CPI · Cost Performance Index
EV ÷ AC
Measure of cost efficiency. A CPI of 1.0 means the project is exactly on budget.
> 1.0 = Under planned cost · = 1.0 = On planned cost · < 1.0 = Over planned cost
SPI · Schedule Performance Index
EV ÷ PV
Measure of schedule efficiency. An SPI of 1.0 means the project is exactly on schedule.
> 1.0 = Ahead of schedule · = 1.0 = On schedule · < 1.0 = Behind schedule
CV · Cost Variance
EV − AC
Amount of budget deficit or surplus at a given point in time.
Positive = Under planned cost · Neutral = On planned cost · Negative = Over planned cost
SV · Schedule Variance
EV − PV
Difference between earned value and planned value — in cost terms.
Positive = Ahead of schedule · Neutral = On schedule · Negative = Behind schedule
EAC · Estimate at Completion
BAC ÷ CPI
Primary — assumes current efficiency holds
AC + (BAC − EV)
Future work at planned rate
AC + [(BAC−EV) ÷ (CPI × SPI)]
Both cost and schedule influence remaining work
TCPI · To-Complete Performance Index
(BAC − EV) ÷ (BAC − AC)
Efficiency needed to finish within original BAC
(BAC − EV) ÷ (EAC − AC)
Efficiency needed to finish within revised EAC
> 1.0 = Harder · = 1.0 = Same · < 1.0 = Easier
VAC · Variance at Completion
BAC − EAC
Projection of the budget deficit or surplus at project completion.
Positive = Under planned cost · Neutral = On planned cost · Negative = Over planned cost
ETC · Estimate to Complete
EAC − AC
Expected cost to finish all remaining project work.
Alternative: reestimate remaining work from the bottom up.
Always verify against your organisation's reporting standards.